SJV Construction was retained by PEEK Properties, Inc., as the supportive excavation engineer for the construction of a new apartment complex in East Orange, NJ. The construction site posed some unique excavation challenges:
Plans called for excavation and construction of lot-line walls, mere feet from a 30-year-old existing building.
This building, an original wood-frame structure with two subsequently built additions, had a large, 3/4" crack that had formed along the butt joint between the additions.
One addition was constructed with 8" block with a return; the other was set on slab-on-grade and was unattached to the original masonry. They were both unfiled and did not meet building code requirements. Of concern was that neither the primary nor the additional masonry had the lateral stabilization typically required.
Given these challenges, SJV's engineer-of-record was concerned that additional movement would be likely to this structure during excavation due to the lack of an appropriate foundation and lateral bracing. He recommended tilt monitoring during excavation and foundation construction to provide continuous information about the movement of the structure during the shoring process.
One Veva III Tilt Monitor was placed on the addition approximately five feet above ground level and in close proximity to the crack to be monitored (see photo 1). Continuous tilt monitoring was provided with hourly recording 24 hours a day. The data uploaded to the Inzwa Cloud platform could be viewed by the engineer-of-record at any time and from any device.
Learn more about Inzwa Veva III
While drilling in the rear of the addition to protect the structure, an object was struck approximately six feet below grade. This was unexpected, as soil engineering analysis previously conducted had indicated no structural elements or protrusions within 18 inches of the wall. Believing it to be a boulder, the excavation continued. However, within an hour the tilt monitor indicated rotational movement of approximately 0.04°, triggering an alert and suspension of drilling.
The contractor mitigated the likelihood of additional movement by relocating the new piles outside the existing footings. Not only were no additional movements of the wall noted after this change - the crack reverted to its original size approximately a week after drilling concluded.
Real-time monitoring with the Veva III gave the engineers on site the data they needed when they needed it to make crucial changes and avoid causing potentially costly damage to the existing structure and delays to the project.
Register for free to Webinar: Implementing Effective Risk-Reduction Vibration Monitoring Programs
Source: Inzwa Case Study
Kilduff Underground Engineering, Inc., was hired to perform design, construction management and vib...
Significant ground movements due to deep surface excavations can seriously impact neighbouring infr...
For the 200,000-square-foot City Center project, full control and full visibility of the vibration...
When you live on the bluffs overlooking the shores of Lake Michigan, retaining walls can be serious...
The installation of a new utility line running 874 feet under the Duchesne River involved shoring w...
The east phase of Denver’s multi-year, North System Renewal Project called for the installation of...
The City of Columbus, OH, is expanding its Southerly Wastewater Treatment Plant (SWWTP) as part of...
IOS Press, a valued Geoengineer.org sponsor, published last year a book by Mandy Korff based on a re...
A 3-story building suddenly collapsed into a canal in West Bengal, a state of India. The structure...
Looking for more information? Fill in the form and we will contact Inzwa for you.