The Resia Ten Oaks development, located at Houston, Texas, consists of four new structures, including three identical 12-story residential buildings and one standalone 6-level parking garage (column loads up to 2,500 kips!).
The primary challenge on this project was developing an economical foundation solution to support the heavy column loads without causing excessive settlements. The second challenge was to develop a foundation system that would allow for the use of a highvolume stormwater network between each of the residential buildings. Lastly, the project team needed an economical solution to support the tower crane in the limited space between the proposed structures.
The soil conditions generally consisted of a few feet of undocumented fill soils underlain by interbedded layers of sandy clay (CL), fat clay (CH), and silty/ clayey sands (SM, and SC) to depths of 80+ ft. The marginal soils were typically encountered to depths of about 20 feet below existing grade, quickly becoming hard/dense at greater depths.
Geopier® developed an engineered solution that addressed all of the project challenges noted above. The solution consisted of installing 1,700+ GeopierX1® piers to depths in the range of 10 to 20 feet below existing grade to reinforce the marginal bearing soils and allow for design bearing pressures of 8 ksf. This design bearing pressure allowed for smaller footings, which saved on project cost and allowed the stormwater network to be installed between the buildings. Geopier’s solution also allowed the tower crane to be supported on a smaller mat that fit between the buildings and the stormwater network.
Learn more about Geopier Solutions
![]() | Ground Improvement for Parking Garages and Residential StructuresThis webinar focus on the engineering challenges associated with the design and construction of parking garage and multi-story residential structures and how Geopier can be used to address those concerns and add value on your next project. |
Ground Improvement for Parking Garages and Residential Structures webinar will focus on the enginee...
Geopier recently launched their own versin of MythBusters under the ASCE website, where they dispel...
Geopier, a division of CMC, recently launched their own version of MythBusters under the ASCE websi...
The new high school will have a footprint area of about 92,000 sq. ft. The facility contains severa...
Over 1,300 Geopier Impact® elements were installed in 29 days to mitigate potential liquefaction se...
Geopier participated in the construction at the Flint Hills Resources Ethanol Plant in Shell Rock,...
The Geopier Impact® system was installed for a 10-story residential building in Puerto Varas, Chile...
Approximately 350, 16-inch Geopier Impact® displacement piers were installed for the Kettering Fire...
Geopier® used a combination of systems to support the proposed structure of a 1-story, high bay war...
Looking for more information? Fill in the form and we will contact Geopier, a division of CMC for you.